Subcontractor Payment Schedule Calculator

Calculate progress payment schedules for subcontractors including retainage withholding, milestone-based payments, and final release amounts.

Formulas Used

Total Earned to Date:
Earned = Mobilization Amount + Materials Stored Amount + (Remaining Work Value × Work Completed %)

Retainage Withheld:
Retainage = (Work Completed Amount + Materials Stored Amount) × Retainage %

Net Earned (After Retainage):
Net Earned = Total Earned − Retainage Withheld

Current Payment Due:
Payment Due = Net Earned − Previously Paid Amount

Milestone Payment (per interval):
Milestone Work Value = (Contract Value − Mobilization) ÷ Number of Milestones
Milestone Payment = Cumulative Net Earned at Milestone − Cumulative Previously Paid

Final Payment:
Final Payment = Balance to Finish + Total Retainage Held

Assumptions & References

  • Retainage is withheld on work completed and materials stored, but not on mobilization payments, consistent with AIA Document A401 and A201 standards.
  • Retainage is fully released upon final completion/closeout (substantial completion release may vary by contract).
  • Milestone schedule assumes equal-interval progress payments; actual schedules may be weighted by trade activity.
  • Materials stored on site must be properly documented and insured per AIA G702/G703 Application for Payment requirements.
  • Many states have prompt payment laws requiring payment within 7–30 days of GC receipt; consult your state's statutes.
  • References: AIA A401-2017 (Subcontract Agreement), AIA G702/G703 (Application and Certificate for Payment), ConsensusDocs 750.
  • This calculator provides estimates only. Consult your contract documents and legal counsel for binding payment terms.